Waymon Pardue, Senior Project Manager, Author at PC Construction https://pcconstruction.com/news/author/wpardue/ Building Stronger, Together Fri, 03 Jun 2022 19:36:12 +0000 en-US hourly 1 https://wordpress.org/?v=6.5.2 https://pcconstruction.com/app/uploads/2022/06/cropped-Site-Icon_02-32x32.jpg Waymon Pardue, Senior Project Manager, Author at PC Construction https://pcconstruction.com/news/author/wpardue/ 32 32 Ribbon Cut on New Treatment Plant for Florida’s Palm Coast https://pcconstruction.com/news/ribbon-cut-on-new-treatment-plant-for-floridas-palm-coast/ Tue, 26 Jun 2018 11:51:56 +0000 https://www.pcconstruction.com/blog/?p=5883 Earlier this month, the City of Palm Coast celebrated the completion of their new wastewater treatment plant. The $30 million dollar facility, which was built by PC Construction, will augment the city’s existing treatment plant, which has neared capacity, and accommodate continued growth and development in the area. The project, which was constructed on a […]

The post Ribbon Cut on New Treatment Plant for Florida’s Palm Coast appeared first on PC Construction.

]]>

Earlier this month, the City of Palm Coast celebrated the completion of their new wastewater treatment plant. The $30 million dollar facility, which was built by PC Construction, will augment the city’s existing treatment plant, which has neared capacity, and accommodate continued growth and development in the area.

The project, which was constructed on a 15-acre greenfield site, included a new membrane bioreactor treatment facility with added reclaimed water storage, headworks, chemical storage and feeders, sludge holding tanks and dewatering facilities, and electrical distribution and controls.

The new facility will provide an additional two million gallons of treatment capacity per day. The resulting high-quality effluent will be used for irrigation and groundwater recharge, allowing the City to conserve potable water and decrease the rate of groundwater withdrawal.

The post Ribbon Cut on New Treatment Plant for Florida’s Palm Coast appeared first on PC Construction.

]]>
Pump Station S-5A Project Reaches Major Milestone https://pcconstruction.com/news/pump-station-s-5a-project-reaches-major-milestone/ Wed, 28 Mar 2018 13:23:19 +0000 https://www.pcconstruction.com/blog/?p=5824 Located in Loxahatchee, Florida, Pump Station S-5A is one of the initial pump stations built by the South Florida Water Management District and was the world’s largest when commissioned in 1955. The pump station has six 1,800-horsepower diesel engines driving six 800 cubic feet per second axial flow pumps via double reduction chain drives for […]

The post Pump Station S-5A Project Reaches Major Milestone appeared first on PC Construction.

]]>
Located in Loxahatchee, Florida, Pump Station S-5A is one of the initial pump stations built by the South Florida Water Management District and was the world’s largest when commissioned in 1955. The pump station has six 1,800-horsepower diesel engines driving six 800 cubic feet per second axial flow pumps via double reduction chain drives for a pumping capacity of 4,800 cubic feet per second or 3,108 mgd.  The pump station building was originally constructed around the engines and pumps.

The second phase of our work includes the removal and refurbishment of the engine, pump and chain drive assemblies. On February 23, we removed the first of six engines, which was placed on a flatbed for transport to Texas for refurbishment. This long-awaited milestone was accomplished with members of the South Florida Water Management District in attendance remarking that this day was 10 years in the making.

On March 6, we removed the final section of the first pump – the lower casing – which had not moved since initial placement over 60 years ago. The casing was removed from the pump station through the existing roll-up door with only a two-inch clearance on each side.

While accomplishing these major project milestones, the PC Construction team celebrated 500 injury-free days on this project.

While the pump and engine are offsite, we continue modifications to the pump station and site. Installation of auxiliary equipment is underway in preparation for the return of the improved engine and pump system.

Top Photo: The first of the six pump station engines ready to make the haul across the country for refurbishment. Bottom Photo: The PC Construction team celebrated 500 injury-free days on this project.

The post Pump Station S-5A Project Reaches Major Milestone appeared first on PC Construction.

]]>